In ProgressGAITAN FIXING MACHINE
📄
Documents are now counted in cost. Review your documents and turn on “Count in project cost” where it is not already included in Manual Cost.
A. Project Info
プロジェクト情報
Invoice 40% / 請求40%
Customer
TOBA (THAILAND) CO.,LTD.
Linked Quote
TOB2609-003-R.1
Responsible
—
Start Date
26-Oct-26
Finish Date
26-Oct-26
Planned Delivery / 納期
20-Jan-27
Customer PO
Delivery Planning
納期計画
26-Dec-2026
PO Received
26-Oct-2026
Lead Time
2 months
Est. Delivery
26-Dec-2026
Buffer
+25 days ✓
Payment Tracking / 入金管理
| Milestone | Expected Amount | Expected Date | Invoice Date | Received | Received Date |
|---|---|---|---|---|---|
| After PO (40%) | ฿170,800 | 25-Nov-26 | |||
| After Check (40%) | ฿170,800 | 06-Jan-27 | |||
| After Delivery (0%) | ฿0 | 20-Jan-27 | |||
| After Installation (20%) | ฿85,400 | 19-Feb-27 |
฿170,800 invoiced of ฿427,000 total · 40%
Total Received: ฿170,800 / ฿427,000
Outstanding: ฿256,200
📅 Project Schedule
プロジェクトスケジュール(ガントチャート)
November 2026
No tasks added yet.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Today
No tasks to display
Budget & Cost Tracking
Cost Budget = Sale Price × (1 − Margin%) · Total Actual = Manual Cost + Doc Cost
Apply margin to all items:%
Discount Display / 値引き表示方法:
No discount on linked quotationOverride:
| No. | Description | Sale Price (฿) | Margin % | Cost Budget (฿) | Manual Cost (฿) | Doc Cost (฿) | Total Actual (฿) | Variance (฿) |
|---|---|---|---|---|---|---|---|---|
| 1 | Design ME | ฿20,000 | ⚠️ | ฿20,000 | — | ฿0 | ▲ ฿20,000 | |
| 2 | Design EE | ฿15,000 | ⚠️ | ฿15,000 | — | ฿0 | ▲ ฿15,000 | |
| 3 | Purchase part EE | ฿55,000 | ⚠️ | ฿55,000 | — | ฿0 | ▲ ฿55,000 | |
| 4 | Purchase part M/C | ฿12,000 | ⚠️ | ฿12,000 | — | ฿0 | ▲ ฿12,000 | |
| 5 | Production Parts M/C | ฿63,000 | ⚠️ | ฿63,000 | — | ฿0 | ▲ ฿63,000 | |
| 6 | COVER UV protection ( Use Polycarbonate (PC) 5mm ) | ฿36,000 | ⚠️ | ฿36,000 | — | ฿0 | ▲ ฿36,000 | |
| 7 | MODIFY Old Machine ( Top frame cut 300-400mm) | ฿11,000 | ⚠️ | ฿11,000 | — | ฿0 | ▲ ฿11,000 | |
| 8 | Support JIG&TOOL Unit | ฿56,000 | ⚠️ | ฿56,000 | — | ฿0 | ▲ ฿56,000 | |
| 9 | Wiring | ฿25,000 | ⚠️ | ฿25,000 | — | ฿0 | ▲ ฿25,000 | |
| 10 | ASSEMBLY | ฿32,000 | ⚠️ | ฿32,000 | — | ฿0 | ▲ ฿32,000 | |
| 11 | PLC Program | ฿60,000 | ⚠️ | ฿60,000 | — | ฿0 | ▲ ฿60,000 | |
| 12 | TEST RUN | ฿30,000 | ⚠️ | ฿30,000 | — | ฿0 | ▲ ฿30,000 | |
| 13 | Overhead & Delivery | ฿12,000 | ⚠️ | ฿12,000 | — | ฿0 | ▲ ฿12,000 | |
| Net Total / 正味合計 | ฿427,000 | 0.0% avg | ฿427,000 | ฿0 | ฿0 | ฿0 | ▲ ฿427,000 | |
D. Work Hours
作業時間
| Date | Task Description | Person | Hours | Rate (฿/hr) | Labor Cost | |
|---|---|---|---|---|---|---|
| No work hours logged yet. | ||||||
📎 Project Documents
Invoices, purchase orders, delivery notes, specs, and other cost-related files
Drag files here or click to browse
Accepted: PDF, JPG, PNG, WEBP, XLSX, XLS, CSV, DOCX, DOC · Max 20MB per file · Max 30 files
Counted in cost: ฿0 (0 docs)·Not counted: ฿0 (0 docs)·Counted but unallocated: ฿0 (0 docs)
No documents uploaded yet.
F. Estimated P&L (Estimated)
推定P&L
REVENUE
Sale Price (Quote Total):฿427,000
MATERIAL COST
Manual cost (entered in the Budget table)฿0
From documents (linked to items)฿0
From documents (unallocated)฿0
Estimated items (no cost recorded yet)est.฿427,000
= Total Material Cost:฿427,000
OTHER COSTS
Labor Cost:฿0
Total Cost:฿427,000
* Items with no cost recorded use Cost Budget as an estimate.
Gross Profit
฿0
▲ 0.0%
Gross Margin
(Estimated)