WINDOW POSSITION INSPECTION MACHINE

A. Project Info

プロジェクト情報

Invoice 40% / 請求40%

Customer

TOBA (THAILAND) CO.,LTD.

Linked Quote

TOB2608-005

Responsible

Mr. padungsak

Start Date

15-Sep-26

Planned Delivery / 納期

15-Nov-26

Customer PO

Customer PO No.PO26-09-0539
PO Date15-Sep-26
PO Amount฿685,000
1592-PO26-09-0539-WINDOW POSSITION INSPECTION MACHINE.pdf Download

Delivery Planning

納期計画

Buffer is less than 7 days.

15-Nov-2026

PO Received

15-Sep-2026

Lead Time

2 months

Est. Delivery

15-Nov-2026

Buffer

On deadline

Payment Tracking / 入金管理

MilestoneExpected AmountExpected DateInvoice DateReceivedReceived Date
After PO (40%)฿274,00015-Oct-26
After Check (40%)฿274,00001-Nov-26
After Delivery (0%)฿015-Nov-26
After Installation (20%)฿137,00015-Dec-26

฿274,000 invoiced of ฿685,000 total · 40%

Total Received: ฿274,000 / ฿685,000
Outstanding: ฿411,000

📅 Project Schedule

プロジェクトスケジュール(ガントチャート)

Total Tasks

3

Completed

0

In Progress

3

Delayed

0

✓ On Schedule
September 2026
—
—
—
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Today

Budget & Cost Tracking

Set margin % per item. Cost Budget = Sale Price × (1 − Margin%)

Apply margin to all items:%
No.DescriptionSale Price (฿)Margin %Cost Budget (฿)Actual Spent (฿)Variance (฿)
1Production Parts M/C฿205,000
฿184,500
▲ ฿184,500
2Purchase Parts M/C฿109,000
฿98,100
▲ ฿98,100
3Purchase Part EE฿85,000
฿76,500
▲ ฿76,500
4Assembly machine฿35,000
฿31,500
▲ ฿31,500
5Electric Design฿25,000
฿22,500
▲ ฿22,500
6Wiring฿25,000
฿22,500
▲ ฿22,500
7PLC Program฿50,000
฿45,000
▲ ฿45,000
8DATA data logging฿60,000
฿54,000
▲ ฿54,000
9Installation฿36,000
฿32,400
▲ ฿32,400
10Test run฿45,000
฿40,500
▲ ฿40,500
11OH฿10,000
฿9,000
▲ ฿9,000
PROJECT TOTAL฿685,00010.0% avg฿616,500฿0▲ ฿616,500

D. Work Hours

作業時間

DateTask DescriptionPersonHoursRate (฿/hr)Labor Cost
No work hours logged yet.

📎 Project Documents

Invoices, purchase orders, delivery notes, specs, and other cost-related files

Drag files here or click to browse

Accepted: PDF, JPG, PNG, WEBP, XLSX, XLS, CSV, DOCX, DOC · Max 20MB per file · Max 30 files

No documents uploaded yet.

F. Estimated P&L (Estimated)

推定P&L

Estimated

REVENUE

Sale Price (Quote Total):฿685,000

COSTS (using Budget estimate)

Material Cost*:฿616,500
Labor Cost:฿0
Total Cost:฿616,500

* Some rows use Cost Budget as estimate (no Actual Spent entered)

Gross Profit
฿68,500
▲ 10.0%
Gross Margin
(Estimated)