1592
In ProgressWINDOW POSSITION INSPECTION MACHINE (EPSON)
📄
Documents are now counted in cost. Review your documents and turn on “Count in project cost” where it is not already included in Manual Cost.
A. Project Info
プロジェクト情報
Invoice 80% / 請求80%
Customer
TOBA (THAILAND) CO.,LTD.
Linked Quote
TOB2608-005
Responsible
Mr. padungsak
Start Date
15-Sep-26
Planned Delivery / 納期
19-Nov-26
Customer PO
Customer PO No.PO26-09-0539
PO Date15-Sep-26
PO Amount฿685,000
1592-PO26-09-0539-WINDOW POSSITION INSPECTION MACHINE.pdf Download
Delivery Planning
納期計画
Buffer is less than 7 days.
15-Nov-2026
PO Received
15-Sep-2026
Lead Time
2 months
Est. Delivery
15-Nov-2026
Buffer
+4 days ✓
Payment Tracking / 入金管理
| Milestone | Expected Amount | Expected Date | Invoice Date | Received | Received Date |
|---|---|---|---|---|---|
| After PO (40%) | ฿274,000 | 15-Oct-26 | |||
| After Check (40%) | ฿274,000 | 05-Nov-26 | |||
| After Delivery (0%) | ฿0 | 19-Nov-26 | |||
| After Installation (20%) | ฿137,000 | 19-Dec-26 |
฿548,000 invoiced of ฿685,000 total · 80%
Total Received: ฿548,000 / ฿685,000
Outstanding: ฿137,000
📅 Project Schedule
プロジェクトスケジュール(ガントチャート)
Total Tasks
3
Completed
0
In Progress
0
Delayed
✗ Behind Schedule3
November 2026
⚠️ Late
⚠️ Late
⚠️ Late
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Today
Budget & Cost Tracking
Cost Budget = Sale Price × (1 − Margin%) · Total Actual = Manual Cost + Doc Cost
Apply margin to all items:%
Discount Display / 値引き表示方法:
No discount on linked quotationOverride:
| No. | Description | Sale Price (฿) | Margin % | Cost Budget (฿) | Manual Cost (฿) | Doc Cost (฿) | Total Actual (฿) | Variance (฿) |
|---|---|---|---|---|---|---|---|---|
| 1 | Production Parts M/C | ฿205,000 | ฿184,500 | — | ฿0 | ▲ ฿184,500 | ||
| 2 | Purchase Parts M/C | ฿109,000 | ฿98,100 | — | ฿0 | ▲ ฿98,100 | ||
| 3 | Purchase Part EE | ฿85,000 | ฿76,500 | — | ฿0 | ▲ ฿76,500 | ||
| 4 | Assembly machine | ฿35,000 | ฿31,500 | — | ฿0 | ▲ ฿31,500 | ||
| 5 | Electric Design | ฿25,000 | ฿22,500 | — | ฿0 | ▲ ฿22,500 | ||
| 6 | Wiring | ฿25,000 | ฿22,500 | — | ฿0 | ▲ ฿22,500 | ||
| 7 | PLC Program | ฿50,000 | ฿45,000 | — | ฿0 | ▲ ฿45,000 | ||
| 8 | DATA data logging | ฿60,000 | ฿54,000 | — | ฿0 | ▲ ฿54,000 | ||
| 9 | Installation | ฿36,000 | ฿32,400 | — | ฿0 | ▲ ฿32,400 | ||
| 10 | Test run | ฿45,000 | ฿40,500 | — | ฿0 | ▲ ฿40,500 | ||
| 11 | OH | ฿10,000 | ฿9,000 | — | ฿0 | ▲ ฿9,000 | ||
| Net Total / 正味合計 | ฿685,000 | 10.0% avg | ฿616,500 | ฿0 | ฿0 | ฿0 | ▲ ฿616,500 | |
D. Work Hours
作業時間
| Date | Task Description | Person | Hours | Rate (฿/hr) | Labor Cost | |
|---|---|---|---|---|---|---|
| No work hours logged yet. | ||||||
📎 Project Documents
Invoices, purchase orders, delivery notes, specs, and other cost-related files
Drag files here or click to browse
Accepted: PDF, JPG, PNG, WEBP, XLSX, XLS, CSV, DOCX, DOC · Max 20MB per file · Max 30 files
Counted in cost: ฿0 (0 docs)·Not counted: ฿0 (9 docs)·Counted but unallocated: ฿0 (0 docs)
| File Name | Category | Vendor | Doc No. | Amount ex-VAT (฿) | Counted in cost | Linked item | Upload Date | Uploaded By | Actions | |
|---|---|---|---|---|---|---|---|---|---|---|
| S__121749508_0.jpg | 🖼️ Photo / Drawing | — | — | — | — | 19-Nov-26 | — | |||
| S__121749509_0.jpg | 🖼️ Photo / Drawing | — | — | — | — | 19-Nov-26 | — | |||
| S__121749510_0.jpg | 🖼️ Photo / Drawing | — | — | — | — | 19-Nov-26 | — | |||
| S__121815048_0.jpg | 🖼️ Photo / Drawing | — | — | — | — | 19-Nov-26 | — | |||
| S__121815045_0.jpg | 🖼️ Photo / Drawing | — | — | — | — | 19-Nov-26 | — | |||
| S__121815046_0.jpg | 🖼️ Photo / Drawing | — | — | — | — | 19-Nov-26 | — | |||
| S__121815043_0.jpg | 🖼️ Photo / Drawing | — | — | — | — | 19-Nov-26 | — | |||
| S__121815047_0.jpg | 🖼️ Photo / Drawing | — | — | — | — | 19-Nov-26 | — | |||
| S__121815044_0.jpg | 🖼️ Photo / Drawing | — | — | — | — | 19-Nov-26 | — |
F. Estimated P&L (Estimated)
推定P&L
REVENUE
Sale Price (Quote Total):฿685,000
MATERIAL COST
Manual cost (entered in the Budget table)฿0
From documents (linked to items)฿0
From documents (unallocated)฿0
Estimated items (no cost recorded yet)est.฿616,500
= Total Material Cost:฿616,500
OTHER COSTS
Labor Cost:฿0
Total Cost:฿616,500
* Items with no cost recorded use Cost Budget as an estimate.
Gross Profit
฿68,500
▲ 10.0%
Gross Margin
(Estimated)