6759
CompletedPROGRAMIMG FOR 2PMMC FULL AUTO ASSEMBLY SYSTEM
A. Project Info
プロジェクト情報
Customer
OHM DENKI (THAILAND) LTD.
Linked Quote
OHM2609-001-R.1
Responsible
—
Start Date
11-Sep-26
Planned Delivery / 納期
—
Customer PO
Customer PO No.
OE09/0085
PO Date
10-Sep-26
PO Amount
฿98,000
PO Document
6759 ohm denki.pdf
Delivery Planning
納期計画
10-Sep-2026
20 days
30-Sep-2026
—
PO Received
10-Sep-2026
Lead Time
20 days
Est. Delivery
30-Sep-2026
Buffer
—
Payment Tracking / 入金管理
| Milestone | Expected Amount | Expected Date | Invoice Date | Received | Received Date |
|---|---|---|---|---|---|
| After PO (40%) | ฿39,200 | 10-Oct-26 | |||
| After Check (0%) | ฿0 | 16-Sep-26 | |||
| After Delivery (60%) | ฿58,800 | 30-Sep-26 | |||
| After Installation (0%) | ฿0 | 30-Oct-26 |
฿98,000 invoiced of ฿98,000 total · 100%
📅 Project Schedule
プロジェクトスケジュール(ガントチャート)
No tasks added yet.
Budget & Cost Tracking
Cost Budget = Sale Price × (1 − Margin%) · Total Actual = Manual Cost + Doc Cost
| No. | Description | Sale Price (฿) | Margin % | Cost Budget (฿) | Manual Cost (฿) | Doc Cost (฿) | Total Actual (฿) | Variance (฿) |
|---|---|---|---|---|---|---|---|---|
| PROGRAMIMG FOR 2PMMC FULL AUTO ASSEMBLY SYSTEM | ฿115,000 | 10.0% avg | ฿103,500 | ฿0 | ฿0 | ฿0 | ▲ ฿103,500 | |
| 1 | Program PLC & HMI | ฿90,000 | 10% | ฿81,000 | — | ฿0 | ▲ ฿81,000 | |
| 2 | Test run and transportation | ฿20,000 | 10% | ฿18,000 | — | ฿0 | ▲ ฿18,000 | |
| 3 | Overhead profit | ฿5,000 | 10% | ฿4,500 | — | ฿0 | ▲ ฿4,500 | |
| Discount (Fixed) | −฿17,000 | — | — | — | — | — | — | |
| Net Total / 正味合計 | ฿115,000 | 10.0% avg | ฿103,500 | ฿0 | ฿0 | ฿0 | ▲ ฿103,500 | |
D. Work Hours
作業時間
| Date | Task Description | Person | Hours | Rate (฿/hr) | Labor Cost | |
|---|---|---|---|---|---|---|
| ฿2,400 |
Total Hours
4.0 hrs
Total Labor Cost
฿2,400
Average Hourly Rate
฿600/hr
After-Service (Non-Billable)
アフターサービス(請求対象外)
📎 Project Documents
Invoices, purchase orders, delivery notes, specs, and other cost-related files
F. Final P&L ✓
最終P&L
REVENUE
MATERIAL COST
OTHER COSTS
3 items have no cost recorded and counts as 0 in this final P&L.