0271
CompletedJIG GUARD WELDING MODEL A,B,C,D,E
A. Project Info
プロジェクト情報
Customer
M.S. TRADING EU HUA GUANG JEAR SUNG CO., LTD.
Linked Quote
MST2605-001
Responsible
—
Start Date
23-Jul-26
Planned Delivery / 納期
23-Aug-26
Customer PO
Customer PO No.
PO2026070019
PO Date
23-Jul-26
PO Amount
฿33,600
PO Document
0271-PO2026070019_Haru_Daikin Com (SH7142)_Jig Guard Welding Model A,B,C,D,E.pdf
Delivery Planning
納期計画
23-Jul-2026
1 months
23-Aug-2026
23-Aug-2026
PO Received
23-Jul-2026
Lead Time
1 months
Est. Delivery
23-Aug-2026
Buffer
On deadline
Payment Tracking / 入金管理
| Milestone | Expected Amount | Expected Date | Invoice Date | Received | Received Date |
|---|---|---|---|---|---|
| After PO (0%) | ฿0 | 22-Aug-26 | |||
| After Check (0%) | ฿0 | 09-Aug-26 | |||
| After Delivery (100%) | ฿33,600 | 23-Aug-26 | |||
| After Installation (0%) | ฿0 | 22-Sep-26 |
฿33,600 invoiced of ฿33,600 total · 100%
📅 Project Schedule
プロジェクトスケジュール(ガントチャート)
No tasks added yet.
Budget & Cost Tracking
Cost Budget = Sale Price × (1 − Margin%) · Total Actual = Manual Cost + Doc Cost
| No. | Description | Sale Price (฿) | Margin % | Cost Budget (฿) | Manual Cost (฿) | Doc Cost (฿) | Total Actual (฿) | Variance (฿) |
|---|---|---|---|---|---|---|---|---|
| 1 | H1-0586-A60-01-01 (A+B) | ฿11,600 | 0% | ฿11,600 | — | ฿0 | ▲ ฿11,600 | |
| 2 | H1-0586-A60-01-02 (A+B) | ฿1,500 | 0% | ฿1,500 | — | ฿0 | ▲ ฿1,500 | |
| 3 | H1-0586-A60-01-08 (C) | ฿5,500 | 0% | ฿5,500 | — | ฿0 | ▲ ฿5,500 | |
| 4 | ้H1-0586-A60-01-09 (C) | ฿1,000 | 0% | ฿1,000 | — | ฿0 | ▲ ฿1,000 | |
| 5 | H1-0586-A60-04 (D) | ฿6,500 | 0% | ฿6,500 | — | ฿0 | ▲ ฿6,500 | |
| 6 | H1-0586-A60-01-05 (D) | ฿1,000 | 0% | ฿1,000 | — | ฿0 | ▲ ฿1,000 | |
| 7 | H1-0586-A60-01-06 (D) | ฿500 | 0% | ฿500 | — | ฿0 | ▲ ฿500 | |
| 8 | H1-0586-A60-01-11 (E) | ฿6,000 | 0% | ฿6,000 | — | ฿0 | ▲ ฿6,000 | |
| Net Total / 正味合計 | ฿33,600 | 0.0% avg | ฿33,600 | ฿0 | ฿0 | ฿0 | ▲ ฿33,600 | |
D. Work Hours
作業時間
| Date | Task Description | Person | Hours | Rate (฿/hr) | Labor Cost | |
|---|---|---|---|---|---|---|
| No work hours logged yet. | ||||||
After-Service (Non-Billable)
アフターサービス(請求対象外)
📎 Project Documents
Invoices, purchase orders, delivery notes, specs, and other cost-related files
F. Final P&L ✓
最終P&L
REVENUE
MATERIAL COST
OTHER COSTS
8 items have no cost recorded and counts as 0 in this final P&L.