1571
CompletedADDITION FOR COPELAND
A. Project Info
プロジェクト情報
Customer
M.S. TRADING EU HUA GUANG JEAR SUNG CO., LTD.
Linked Quote
MST2606-005
Responsible
—
Start Date
08-Jul-26
Planned Delivery / 納期
25-Jul-26
Notes
Addition
Customer PO
Customer PO No.
PO2026070003
PO Date
08-Jul-26
PO Amount
฿147,600
PO Document
PO2026070003_Haru_Copeland (Advance Order)(QJ-2026-06-0101,QJ-2026-06-0102)_Addition For Copeland.pdf
Delivery Planning
納期計画
08-Jul-2026
0 days
—
25-Jul-2026
PO Received
08-Jul-2026
Lead Time
0 days
Est. Delivery
—
Buffer
—
Payment Tracking / 入金管理
| Milestone | Expected Amount | Expected Date | Invoice Date | Received | Received Date |
|---|---|---|---|---|---|
| After PO (40%) | ฿59,040 | 07-Aug-26 | |||
| After Check (0%) | ฿0 | 11-Jul-26 | |||
| After Delivery (0%) | ฿0 | 25-Jul-26 | |||
| After Installation (60%) | ฿88,560 | 24-Aug-26 |
฿147,600 invoiced of ฿147,600 total · 100%
📅 Project Schedule
プロジェクトスケジュール(ガントチャート)
No tasks added yet.
Budget & Cost Tracking
Cost Budget = Sale Price × (1 − Margin%) · Total Actual = Manual Cost + Doc Cost
| No. | Description | Sale Price (฿) | Margin % | Cost Budget (฿) | Manual Cost (฿) | Doc Cost (฿) | Total Actual (฿) | Variance (฿) |
|---|---|---|---|---|---|---|---|---|
| 1 | Production Parts MC | ฿8,600 | 15% | ฿7,310 | — | ฿0 | ▲ ฿7,310 | |
| 2 | Purchase Parts MC | ฿37,500 | 15% | ฿31,875 | — | ฿0 | ▲ ฿31,875 | |
| 3 | Purchase Parts EE | ฿25,000 | 15% | ฿21,250 | — | ฿0 | ▲ ฿21,250 | |
| 4 | Mecha Design | ฿7,500 | 15% | ฿6,375 | — | ฿0 | ▲ ฿6,375 | |
| 5 | Wiring | ฿12,000 | 15% | ฿10,200 | — | ฿0 | ▲ ฿10,200 | |
| 6 | PLC Program Modify | ฿8,000 | 15% | ฿6,800 | — | ฿0 | ▲ ฿6,800 | |
| 7 | Installation & Test run | ฿40,000 | 15% | ฿34,000 | — | ฿0 | ▲ ฿34,000 | |
| 8 | OH | ฿9,000 | 15% | ฿7,650 | — | ฿0 | ▲ ฿7,650 | |
| Net Total / 正味合計 | ฿147,600 | 15.0% avg | ฿125,460 | ฿0 | ฿0 | ฿0 | ▲ ฿125,460 | |
D. Work Hours
作業時間
| Date | Task Description | Person | Hours | Rate (฿/hr) | Labor Cost | |
|---|---|---|---|---|---|---|
| No work hours logged yet. | ||||||
After-Service (Non-Billable)
アフターサービス(請求対象外)
📎 Project Documents
Invoices, purchase orders, delivery notes, specs, and other cost-related files
F. Final P&L ✓
最終P&L
REVENUE
MATERIAL COST
OTHER COSTS
8 items have no cost recorded and counts as 0 in this final P&L.