1591
CompletedRUBBER PLATE PREHEAT AND DRY SYSTEM
A. Project Info
プロジェクト情報
Customer
KASAN CORPORATION CO.,LTD.
Linked Quote
KAS2605-002
Responsible
Kittithat
Start Date
29-May-26
Finish Date
15-Oct-26
Planned Delivery / 納期
29-Oct-26
Customer PO
Customer PO No.
SKPI26050181
PO Date
29-May-26
PO Amount
฿1,739,100
PO Document
1591 PO.pdf
Delivery Planning
納期計画
29-May-2026
4 months
29-Sep-2026
29-Oct-2026
PO Received
29-May-2026
Lead Time
4 months
Est. Delivery
29-Sep-2026
Buffer
+30 days ✓
Payment Tracking / 入金管理
| Milestone | Expected Amount | Expected Date | Invoice Date | Received | Received Date |
|---|---|---|---|---|---|
| After PO (50%) | ฿869,550 | 28-Jun-26 | |||
| After Check (40%) | ฿695,640 | 15-Oct-26 | |||
| After Delivery (0%) | ฿0 | 29-Oct-26 | |||
| After Installation (10%) | ฿173,910 | 28-Nov-26 |
฿1,739,100 invoiced of ฿1,739,100 total · 100%
📅 Project Schedule
プロジェクトスケジュール(ガントチャート)
No tasks added yet.
Budget & Cost Tracking
Cost Budget = Sale Price × (1 − Margin%) · Total Actual = Manual Cost + Doc Cost
| No. | Description | Sale Price (฿) | Margin % | Cost Budget (฿) | Manual Cost (฿) | Doc Cost (฿) | Total Actual (฿) | Variance (฿) |
|---|---|---|---|---|---|---|---|---|
| 1 | General parts of Heater | ฿7,650 | 15% | ฿6,503 | — | ฿0 | ▲ ฿6,503 | |
| 2 | Electric Air Blower | ฿221,850 | 15% | ฿188,573 | — | ฿189,000 | ▼ ฿428 | |
| 3 | Frame | ฿239,700 | 15% | ฿203,745 | — | ฿80,186 | ▲ ฿123,559 | |
| 4 | Purchase Parts | ฿346,800 | 15% | ฿294,780 | — | ฿226,980 | ▲ ฿67,800 | |
| 5 | Purchase Parts EE( OP BOX , Control BOX ) | ฿543,150 | 15% | ฿461,678 | — | ฿295,632 | ▲ ฿166,045 | |
| 6 | Mecha Design | ฿44,200 | 15% | ฿37,570 | — | ฿52,800 | ▼ ฿15,230 | |
| 7 | PLC Program | ฿24,650 | 15% | ฿20,953 | — | ฿26,100 | ▼ ฿5,148 | |
| 8 | Mecha Assembly 3 machine | ฿106,250 | 15% | ฿90,313 | — | ฿173,700 | ▼ ฿83,388 | |
| 9 | Wiring 3 machine | ฿68,000 | 15% | ฿57,800 | — | ฿73,500 | ▼ ฿15,700 | |
| 10 | Test run 3 machine | ฿35,700 | 15% | ฿30,345 | — | ฿60,000 | ▼ ฿29,655 | |
| 11 | Installation 3 machine | ฿62,900 | 15% | ฿53,465 | — | ฿0 | ▲ ฿53,465 | |
| 12 | OH and Delivery | ฿38,250 | 15% | ฿32,513 | — | ฿0 | ▲ ฿32,513 | |
| Net Total / 正味合計 | ฿1,739,100 | 15.0% avg | ฿1,478,235 | ฿1,177,898 | ฿0 | ฿1,177,898 | ▲ ฿300,337 | |
D. Work Hours
作業時間
| Date | Task Description | Person | Hours | Rate (฿/hr) | Labor Cost | |
|---|---|---|---|---|---|---|
| No work hours logged yet. | ||||||
After-Service (Non-Billable)
アフターサービス(請求対象外)
📎 Project Documents
Invoices, purchase orders, delivery notes, specs, and other cost-related files
F. Final P&L ✓
最終P&L
REVENUE
MATERIAL COST
OTHER COSTS
3 items have no cost recorded and counts as 0 in this final P&L.