Projects

プロジェクト

Admin User
管理者

6751

Completed

PALLETIZING ROBOT SYSTEM MODIFY

✓ Project Completed

A. Project Info

プロジェクト情報

Payment/Done / 入金完了

Customer

DAIICHI JITSUGYO (THAILAND) CO.,LTD.

Linked Quote

DJK2607-001

Responsible

—

Start Date

01-Jul-26

Planned Delivery / 納期

01-Sep-26

Customer PO

Customer PO No.

553-2607-003

PO Date

01-Jul-26

PO Amount

฿634,000

PO Document

6751 PO.pdf

Customer PO No.553-2607-003
PO Date01-Jul-26
PO Amount฿634,000
6751 PO.pdf Download

Delivery Planning

納期計画

Buffer is less than 7 days.

01-Jul-2026

2 months

01-Sep-2026

01-Sep-2026

PO Received

01-Jul-2026

Lead Time

2 months

Est. Delivery

01-Sep-2026

Buffer

On deadline

Payment Tracking / 入金管理

MilestoneExpected AmountExpected DateInvoice DateReceivedReceived Date
After PO (40%)฿253,60031-Jul-26—✓ Received08-Jul-26
After Check (40%)฿253,60018-Aug-26—✓ Received18-Aug-26
After Delivery (0%)฿001-Sep-26—○ Pending—
After Installation (20%)฿126,80001-Oct-26—✓ Received18-Aug-26

฿634,000 invoiced of ฿634,000 total · 100%

Total Received: ฿634,000 / ฿634,000
Outstanding: ฿0

📅 Project Schedule

プロジェクトスケジュール(ガントチャート)

Total Tasks

8

Completed

0

In Progress

0

Delayed

0

✓ On Schedule
September 2026
—Data check (PLC, HMI, Electric drawing , Robot program)
—Show data result of similarity percent from Vision sensor VS20M-13F410 on HMI screen
—Modify wrapping machine alarm robot stop
—Opearate rewrapping reverse conveyor.
—Purchase parts electrics and wiring
—Motor roller for NG chute
—Safety fence modify
—Cover NG chute
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Today

Budget & Cost Tracking

Set margin % per item. Cost Budget = Sale Price × (1 − Margin%)

No.DescriptionSale Price (฿)Margin %Cost Budget (฿)Actual Spent (฿)Variance (฿)
1Data check (PLC, HMI, Electric drawing , Robot program) ฿80,0000%฿80,000
฿0
▲ ฿80,000
2Show data result of similarity percent from Vision sensor VS20M-13F410 on HMI screen ฿40,0000%฿40,000
฿0
▲ ฿40,000
3Modify wrapping machine alarm robot stop ฿50,0000%฿50,000
฿0
▲ ฿50,000
4Opearate rewrapping reverse conveyor. ฿80,0000%฿80,000
฿0
▲ ฿80,000
5Purchase parts electrics and wiring ฿45,0000%฿45,000
฿0
▲ ฿45,000
6Motor roller for NG chute ฿259,00030%฿181,300
฿0
▲ ฿181,300
7Safety fence modify ฿65,0000%฿65,000
฿0
▲ ฿65,000
8Cover NG chute ฿15,0000%฿15,000
฿0
▲ ฿15,000
PROJECT TOTAL฿634,00012.3% avg฿556,300฿0▲ ฿556,300

D. Work Hours

作業時間

DateTask DescriptionPersonHoursRate (฿/hr)Labor Cost
No work hours logged yet.

After-Service (Non-Billable)

アフターサービス(請求対象外)

No after-service records. Use "Add Item" if any non-billable work was done after closing.

📎 Project Documents

Invoices, purchase orders, delivery notes, specs, and other cost-related files

No documents uploaded yet.

F. Final P&L ✓

最終P&L

✓ Final

REVENUE

Sale Price (Quote Total):฿634,000

COSTS

Material Cost:฿0
Labor Cost:฿0
Total Cost:฿0
Gross Profit
฿634,000
▲ 100.0%
Gross Margin
(Final)
base44